Marking
Silerele have marked as DIBT (Deutsches Institut für Bautechnik) DIN 19 560, class of fire resistance, as SSIV mark.
Siler type pipes are made of a special, patented sound-absorbing that guarantee maximum noise reduction in any installation.
SILERELE is an ideal solution for high-rise apartments and where required a minimum of nois
The data relating to acoustic insulation is based on measurements made Freaunhofer - Institut fur Bauphysikdin Stuttgart - in accordance with the conditions specified in test certificate P-BA 113/2004e
Installation of concrete mix
Small distribution systems in toilets and kitchens, the pipeline can picture directly in concrete (cement, does not allow expansion). In terms of pipeline through which water circulates at high temperatures is recommended to be covered with corrugated cardboard to allow dilation.
Fixing pipes
In terms of pipeline through which water circulates at high temperatures is recommended to be covered with corrugated cardboard to allow dilation.
Instructions for fixing installations vertical (columns) and horizontal.
1. Anchor the pipe, the distance between fixing clips should be 10 times the diameter of the pipe.
Vertical pipe must be set at distances of 1m to 2min depending on diameter pipe is installed.
2. Fit clamps on the wall building.
3. The vertical pipe passing through the various floors, we recommend installing a sliding clamp near the jack and another above the recommended distance. In this case, fixing it in the floor itself is a fixed anchor punt.
4. If floor crossing is through a hole then you must install one fixed and one sliding clamp for pipe., Fixed clamps or couplings must be mounted under the sliding sleeves and double mufate on the bottom of the pipe.
Joining pipe to socket
The pipe joints will perform the following operations:
1. Clean the plug and check the state seal gasket
2. Clean pipe and fitting ends to be joined
3. Apply lubricant on the heads Valsir pipe and gasket 4. Withdraw tube about 10mm, this space allows compensating expansion in the use of this connection is no longer needed surgery.
Material
Polypropylene addition of various minerals offers high resistance to water at high temperatures.
Installation on site
Siler pipes are available in various lengths which reduces waste to a minimum.
Manson Double mufat
In joining pipes with normal plug to prevent the effects of thermal expansion, pipe must be fully inserted into the socket and then withdrawn 10mm.
Using a double-junction sleeve mufat this operation is not necessary because the construction of special form of the inside sleeve compensates observational dilation, thus preventing waste of time and ensure a better seal.
Gasket provided.
Pipes and fittings Siler plugs are provided with the gasket at the factory introduced special mufei.Un into place such a system combining ease pipes and fittings and secure seal. .
Sealing penetrations
Pipelines crossing through floors, ceilings or walls should be ensured by sealing against moisture and thermal noise and acoustic insulation materials.
Fire Protection
When installing pipes and connections that pass through floors or Siler walls, the rules in force relating to fire protection ..
This is accomplished through the use of fire stops, overlapping the pipe crossing area and thus prevent the passage of flames, fire stops within them is made of fireproof material that expands when it comes in contact with a heat source and ‘squeeze bore’ so that fire can not move forward, ie from one floor to another or from one room to another.